What was in dispute

A home was flood damaged during Cyclone Jasper in December 2023. The insurer accepted the claim, paid out the contents and temporary accommodation sums insured, and appointed a builder who carried out strip-out and asbestos removal before commencing repairs, including tiling. The laundry was excluded from the outset because that builder considered it non-compliant as a wet area and would not work on it.

By August 2024 the relationship had broken down. The owner said the work was substandard, did not want the builder returning, and asked to be cash settled for the outstanding repairs and for rectification of what had been done.

Three offers followed. The original builder quoted $60,489 for the outstanding work. A second builder inspected and scoped it at $87,383.54, noting it could not warrant the repairs given how much had already been done by someone else. After the owner raised a list of specific problems, that builder revised its scope to $95,713.39.

The owner rejected all three and relied on a scope from her own builder totalling $623,650, which characterised the dwelling as unsafe, non-compliant and unfit for habitation, and proposed full strip-out, rectification, or demolition and rebuild.

What was determined

AFCA found the insurer's scope reasonably covered the extent of the remaining repairs the insurer was responsible for, and that the owner's did not. Having reviewed the larger document, it agreed with the insurer that it included work fairly described as maintenance, as upgrades the policy did not cover, and as work connected neither to the flood nor to the first builder's repairs.

But the insurer did not simply win. Its scope had been prepared 17 months earlier and so would not reflect current retail prices, and its offer contained no uplift. AFCA directed the insurer to obtain an updated quote against the accepted scope at current retail prices, add the outstanding laundry work, and pay that amount plus a 25 per cent contingency uplift — an uplift it tied specifically to the difficulty of taking over repairs that had commenced and then sat unfinished for 19 months.

The owner also sought temporary accommodation beyond the policy limit, which had been exhausted, and was refused. Among the factors AFCA weighed were the breakdown with the original builder and the owner's pursuit of a settlement based on a scope that did not reasonably reflect the outstanding work. She was awarded $2,000 for non-financial loss, against a cap of $6,300, because parts of the claim ought to have been handled with more empathy given her vulnerability. The determination is published on the AFCA website (determination 12-26-350033, 26 March 2026).

The scope read: a bigger number is not a stronger document

The gap here is roughly six and a half to one. On the previous determination we looked at, a four-to-one gap turned out to be a rates problem with both parties describing the same rooms. This one is the opposite. The documents describe genuinely different work, and the question was which description was right.

The owner's scope did not fail because it was ambitious. It failed because it bundled together things that needed to be kept apart. Flood damage, defective work by the insurer's builder, pre-existing non-compliance, maintenance, and upgrades are four or five different categories of work with different parties responsible for each, and a document that runs them into a single figure invites exactly the response it got.

Separating them is unglamorous and it is most of the job. Every line in a reinstatement scope should be attributable: this item is flood damage, this item is consequential damage from the failed repair, this item is a pre-existing condition, this item is a betterment the owner may want and would fund. A scope built that way survives challenge because each line can be defended or conceded individually. A scope that asserts demolition and rebuild as a global conclusion stands or falls in one piece, and here it fell in one piece.

What actually moved the number

This is the most useful thing in the determination, and it is easy to miss because it happened before the dispute reached AFCA.

In October 2024 the owner responded to the $87,383.54 offer with a list of concrete, checkable problems. Items the scope assumed would be reused had been discarded by the insurer's trades, or removed and left outdoors long enough to weather and rust. The scope specified a laminate kitchen benchtop where the original was hardwood. It treated the living room entry as one door where the opening was double. It omitted the laundry sink and a bathroom side door broken during strip-out. It appeared to leave out cleaning and restoring one bedroom floor and replacing another.

Every one of those is a small, verifiable statement about a physical thing. None of them requires an expert to adjudicate. The builder revised its scope and the offer rose by more than $8,000, and AFCA later recorded that the revised document had picked up several of those items.

So specificity moved the number. The $623,650 document, which said the building was unfit for habitation, did not. That is not a coincidence about this owner or this insurer. Narrow factual corrections are hard to refuse because refusing them requires asserting a contrary fact. Global characterisations are easy to refuse because they can be met with a competing characterisation.

The floating floors

One exchange in this determination should be pinned up in front of anyone about to argue about a repair scope.

The insurer's position was that the front room and main bedroom had floating floors, which made them contents rather than building, and the contents sum insured was gone. The owner said there were no floating floors in the house except in one small lino-floored room. AFCA said that without independent evidence it could not determine who was right.

Consider what was actually in dispute: what a floor was made of. Not causation, not policy construction, not a matter of technical judgement. A physical fact about a building, resolvable by anyone who walked in and lifted a board, and it was still live more than two years after the flood because nobody had recorded it while the floor was there. The strip-out had already happened.

Floor build-up determines whether an item sits under building or contents, which trades are involved, whether the substrate needs attention, and what the reinstatement costs. It is a routine thing to document. It went unrecorded, and the owner lost the item — not on the merits, but for want of evidence about something that had been in front of everybody.

The general point is that scope arguments are won and lost on what was documented before the building changed. Once demolition starts, the opportunity closes permanently.

Why the insurer's scope was found actionable

AFCA gave a specific reason for preferring the insurer's document that deserves more attention than it usually gets. That scope carried items a retail customer normally bears rather than an insurer: builder's margin, statutory home warranty insurance, and site supervision.

This matters more than it sounds. A cash settlement has to be actionable by the owner, which means it has to fund the job the owner will actually have to run. An owner engaging a builder directly pays a margin. In most jurisdictions they need statutory home warranty insurance on work above a threshold. Somebody has to supervise and coordinate the trades, and if the owner is not doing it themselves, that is a line item.

Scopes prepared for an insurer's own repair programme often omit all three, because within that programme they are absorbed elsewhere. Handed to an owner as a settlement figure, the same document is short by a meaningful percentage before a single tile is laid. When reviewing any cash settlement scope, supervision, margin and warranty insurance are among the first things to check for, and their absence is a substantive gap rather than an administrative one.

The 17-month-old quote

The accepted scope had been prepared 17 months before the determination, and AFCA held that it would not reflect current retail prices.

The construction point is that a quote is a price with a date attached. Materials move, labour rates move, and a document that was reasonable when written can be materially short by the time anyone acts on it. Where a matter has run long — and this one ran from December 2023 to March 2026 — the age of the pricing becomes a live issue independent of whether the scope itself is right.

Note also the direction of the finding. AFCA accepted the insurer's description of the work and still required it to be repriced. Scope and price are separable questions, and being right about one does not settle the other.

The path she turned down

In January 2026 the insurer proposed sending a building consultant to prepare a scope for the remaining claim-related repairs, then handing that scope to her own builder to price at market rates.

Set aside how that arrived and whose consultant it would have been. As a method, it is close to correct: an independent party defines the work, the owner's chosen builder prices it, and the two questions stay separate. She declined, having already had multiple assessments and not wanting a further inspection, which is an understandable position after two years.

The outcome she received afterwards was, in substance, the insurer's scope repriced at current rates plus 25 per cent. Whether the earlier route would have produced more is unknowable. What is knowable is that the $623,650 document did not, and that AFCA counted her pursuit of it among the reasons for declining additional temporary accommodation.

AFCA also recorded that she disputed the insurer's line-by-line critique of her scope while acknowledging she has no expertise in construction. A scope has to withstand technical challenge, and withstanding it requires someone who can argue the detail.

What owners can take from it

The order of work matters. Damage, then causation, then repair methodology, then scope, then quantities, then pricing, then contingency. Skipping to a large number at the end does not fix a scope that has not separated flood damage from defective work from maintenance from upgrade.

Specific and checkable beats sweeping and asserted. The corrections that moved this settlement were about a benchtop material, a door count, and items thrown away. The assertion that moved nothing was that the house should be demolished.

Document the building before it changes. Floor build-ups, wall construction, what was there and in what condition. Once strip-out has happened, a question as simple as what the floor was made of may become unanswerable.

And check what a cash settlement scope assumes about who is running the job. Margin, warranty insurance and supervision are all the owner's costs once the money is in their hands, and a scope that leaves them out is not a scope the owner can act on.

Important Limitation

This material is general commentary on construction scope and repair methodology. It is not legal advice, financial product advice, insurance claims handling, claims management, or representation of any party in an insurance matter. West Coast Construction Advisory does not hold an Australian Financial Services Licence and does not provide any service requiring one. Every property and every policy differs. Determinations referred to are summarised in our own words from the published record and turn on their own facts. Nothing here should be relied on as an indication of how any other matter would be decided.